|
Essential Architecture- Amsterdam
|
|||||||||
Building a house in AmsterdamThe foundationBefore a house could be built it was necessary to mark the location of the foundations: "the setting out". To locate their correct position, the builders used planks and painted the intended thickness of the walls onto the planks. Then the trenches were dug for the foundation. The weight of the house had to be evenly distributed over the ground area otherwise construction faults could occur through subsidence. This is particularly the case in Amsterdam because of the high level of the ground water and the peaty soil. The solution was to drive long piles into the ground until they reached the sandplates at a depth of 40 to 60 feet. This was achieved by manpower.
The wooden foundation had to be kept submerged beneath the ground water level to stop the rotting process setting in, and thus avoiding subsidence.
The brickworkThe wooden foundation formed the base for the brick foundation. A brick wedge-shaped structure of about five layers was built on top of the foundation planks; the base being broader than the top. Three kinds of mortar were used. The layers in the "wedge" had a loam mixture between them. The brickwork above the wedge had a chalk or lime mortar, and a hard mortar, consisting of sand, chalk and trass was used in the five or six layers above and below ground level. A harder brick was used here forming a damp course to stop the ground water seeping up into the house causing rising damp.
The carpentryOnly after the bricklayer had completed the cellar walls could the carpenter start to work on the cellar ceiling. The pine beams were anchored into the wall. A temporary work floor was placed on top of the floor beams so that the bricklayer could continue building the sidewalls until he reached the correct height for the next floor.
The ends of the beams were sealed with tar to stop them rotting. The wall anchors kept the beams securely attached in the wall and also stopped the wall from buckling. The roofThen the roof trusses were placed in the correct position and attached to the garret beams. The apex had to be placed before the rafters, tilelathes and tiles could be fitted. Finally the roof tiles were laid and were sealed on the inside with a mortar made from sand, chalk, and pigs' or horsehair. A hoisting beam was attached to two extra collar beams at the front of the house to raise and lower goods and furniture. Lead coated gutters and drainpipes were placed at an angle leading off to the back of the house to catch the rainwater. Building the front and back facadeThe front and back facades were completed last. Scaffolding was placed at the front and the back of the house. The bricklayer and the carpenter had to work together to mark out the location of the doors and windows. The carpenter then made the frames for the doors and windows, so the bricklayer could complete the facades. Meanwhile, the carpenter could make the windows and doors.
Brick houses were also made waterproof by filling the joins between the bricks with a high quality mortar that was water resistant. The decorations
These elements were painted a creamy colour called "Bentheim yellow" because sandstone has the tendency to turn black. |
|||||||||
|
links |
Special thanks to the Amsterdam Bureau of Monuments and Archeology website, http://www.bma.amsterdam.nl | ||||||||
| www.essential-architecture.com | |||||||||